North Harbor Operations Center Modernization
126 pages · 2 addenda · 41 requirements
AI recommendation
Conditional Go
Go if conditions are cleared.
Human decision
Pending
What needs to be resolved
- Contract riskOpen
Liquidated damages of $1,500 per calendar day apply after substantial completion.
Confirm schedule float and legal tolerance before committing to bid.
Review with Legal
Source · General Conditions · p.42
RFP_Main.pdf · General Conditions · p.42
Liquidated damages of $1,500 per calendar day apply after substantial completion.
- Submission complianceMissing
Acknowledge Addenda 1-2 on bid form
Confirm the signed bid form acknowledges both addenda.
Review with Bid Lead
Source · p.03
RFP_Main.pdf · p.03
The bidder shall acknowledge receipt of Addenda 1 through 2 on the signed bid form.
- Bid securityRequired
5% bid bond from Treasury-listed surety
Verify the bond amount, surety eligibility and required form.
Review with Finance
Source · p.14
RFP_Main.pdf · p.14
Each bid shall include a bid bond equal to 5% of the total bid, issued by a Treasury-listed surety.